From the Letter of Intent

The project involves the construction of a new sewer pump station (PS-9) designed to manage wastewater flows from neighborhoods along Alton Road (Basin 28A) and the Mt. Sinai Hospital Complex. The new station will replace outdated, undersized facilities that pose a risk of sanitary sewer overflows during peak flow conditions. The design prioritizes functionality and resilience while incorporating odor control systems and landscaping to minimize neighborhood impact.

  • Construction of a new sewer pump station (PS-9) within the Alton Road right-of-way
  • Installation of a wet well and valve vault
  • Installation of elevated electrical and control equipment above Design Flood Elevation of 9.45 ft NAVD88
  • Installation of a Wager odor control valve and BioRem odor control system
  • Installation of 12 ft high black chain-link perimeter fencing with black vinyl-coated privacy slats
  • Installation of Calusa shrub hedges and resilient landscaping including Sabal palmetto, Clusia rosea, and Muhlenbergia capillaris
  • Construction of an asphalt maintenance driveway
  • Site surfacing with porous 3/4-inch washed stone over filter fabric
  • Installation of low-profile, downward-directed, shielded LED site lighting
  • Installation of a standby generator
  • Construction of a prop. elevated platform with handrails
  • Installation of a prop. trash rack structure
  • Construction of a prop. retaining wall
  • Installation of 24-inch sanitary sewer connection
  • Installation of 8-inch DI water main
  • Site grading and raising of pump station site approximately 2.5 ft
  • Minor demolition of existing landscape area and limited hardscape/pavement