Proposal

Installation of sewer pump station equipment including a new pumpstation, odor management system, electrical equipment, underground utilities, fencing, and landscape screening. The most visible portion will be a new generator located east of the existing building.

From the Letter of Intent

Construction of a new sewer pump station designed to manage wastewater flows from neighborhoods along Alton Road between Dade Boulevard and Chase Avenue. The project includes odor control systems and visual screening measures to minimize community impact.

  • Construction of new sewer pump station
  • Installation of Wager odor control valve
  • Installation of BioRem odor control system
  • Elevation of electrical equipment above required flood elevation
  • Installation of hedges and visibility barriers for visual screening
  • 10 ft high black perimeter fencing with vinyl-coated privacy slats
  • Calusa shrub hedges for landscaping
  • Asphalt maintenance driveway
  • Washed stone site surfacing
  • LED site lighting with glare shields
Staff Recommendation
Staff recommends that the DRB discuss the proposal and provide any recommendations to the City Commission
Key Issues
  • Visual screening from public right of way
  • Minimal above ground changes
  • Resilience to natural events
Project Details